Beginning in January, AEP Ohio crews will be in your neighborhood to replace the underground wire that feeds power to your street lights.
Crews will dig a small pit in the green space between your curb and sidewalk to replace the underground wire that feeds your street light. We'll work directly with Ohio Utility Protection Services to mark public utilities on your property such as electric, gas, phone, cable, water, sewer, etc.
Our goal is to minimize any inconvenience to you. Weather permitting, our landscaping crew will return within two weeks to restore any impacted areas of your yard.
There are four phases of work during this project, with each phase lasting approximately six months. Details are available on the locations of work during each phase.
We truly appreciate your cooperation as we work to power your street lighting and brighten your neighborhood.
Still have questions about this project? Please give us a call at 614.523.7960.
There are four phases of work during this project, with each phase lasting approximately six months.
Phase 1, September 2019 to December 2019: Lincoln Village Phase 2, January 2020 to Spring 2020 Phase 3, Spring 2020 to Fall 2020 Phase 4, Fall 2020 to Spring 2020
The map below showcases which areas will be affected throughout the four phases of this project.
“Remember User ID” helps you log in without having to memorize your ID or look it up every time. When you opt in, we automatically fill in your ID from then on. To avoid unauthorized access, you’ll still have to enter your password.
Your security code is a short word or phrase you set up with our customer service associates to provide extra protection for your online account.
If you have forgotten your security code, please call 800.672.2231.
Please login to manage your account.